Farmers Market Road at 7th Street Ditch Cured-In-Place Pipe Liner

Print
Press Enter to show all options, press Tab go to next option

Project Update: October 20, 2017

The project reached substantial completion on August 23, 2017. The initial walkthrough was conducted on September 21, 2017.  No punchlist items were generated from the initial walkthrough. The testing results show that the liner’s structural properties adhere to the design requirements. The project is performing well under high volumes of precipitation. The final acceptance is scheduled on the BOCC October 17th agenda for their review and consideration