Farmers Market Road at 7th Street Ditch Cured-In-Place Pipe Liner

Print
Press Enter to show all options, press Tab go to next option

Project Update: August 24, 2017

The contractor has completed the installation of the Cured-In-Place Pipe (CIPP) liner.  The post-construction video confirmed an excellent fit.  Rip-rap material has been set adjacent to the upstream end of the pipe and all disturbed areas have been sodded.  The contractor is currently working on site cleanup and the necessary paperwork to close out the project.  Construction of the project is on track to be completed by the end of August, 2017.